Services




Tier 1 Carrier Greenfields

SUMMARY

  • Axicom provided a full SAED suite of site development services in order to acquire, design, build and own 54 greenfield sites nationwide for a tier 1 carrier.
  • Through the use of our SAED services, Axicom was able to provide the tier 1 carrier with the intended sites over a 6 year contract, whilst maintaining substantial cost levels and minimal levels of risk and CAPEX.

Challenge

The tier 1 carrier contracted Axicom to progressively acquire, design, build and own 54 greenfield sites nationally. This required the culmination and application of Axicom SAED solutions surrounding site selection, site acquisition, town planning and regulatory compliance, and architecture design and construction services.

Solution

In order to establish the required sites for the carrier, Axicom utilized a number of SAED services in order to carry out the intended contract. Axicom conducted a scope of works associated with; site identification/ reporting, site acquisition, environment and planning, detailed design, civil construction, carrier SMR works and an as built & EME guide.

Axicom provided a full SAED suite of site development services

For each site, the delivery times for site selection and feasibility averaged around 3 months, total SAED works were around 9 months and the civil site construction had a lead time of 6 weeks on average.

RESULTS

Axicom’s SAED strategy provided the necessary frameworks for the required portfolio to be established for the tier 1 carrier.

All facets of the process from site selection through to site construction and handovers were conducted as per the tier 1 carriers requested delivery profile.